We did use a borrow pit that was better material that we found digging some test holes. It was mostly clay /silt loam and still not anywhere near pure clay. It packed really tight but that was in large part because of the big rock truck that was used. Between the truck and load estimated 100,000 lbs of weight every trip. Lifts were 6-12" at a time. We estimated 1000 yards of material were packed in.