Originally Posted by Bobbss
Steve, tell us more about your plans. How long and tall do you plan on the dam being? How deep do you plan on digging. How good is your dirt? Do you have to do more clearing? The more information the better. Give a detailed plan.

Sure. Using the measuring tool on Google Maps, I estimate the dam would have to be around 75' long and I have a max of 10' for the dam height, per NC regulations. I'm aiming for a min of 10-12' of depth, which I think I already have, maybe more in some locations. The dirt is fantastic, nearly all clay. After a good rain, I can form it into a ball rather easily. I have a few trees that are laid down in the bowl of the pond that need to be cleared, but I'm 95% positive that no more tree work (cutting) needs to be done.

Here's a youtube video I did, kinda showing what I'm working with: https://youtu.be/xzLFToj-0lw