I agree, don't talk to the the Army Core of Engineers at all unless you absolutely need to, not even to ask them "do I?" You don't want to show up on their radar.
That's funny about what you were told from the NRCS. I'm currently working with them now on a new pond project. I think a physical visit to your counties NRCS office is in order. Maybe call ahead and set up a meeting with the person that deals with ponds to ensure that they will be in the office and have time for you.
|
|
|