Well they still haven't been out to shoot the grade.They've been rained out and last week it was food poisoning.They said they would try for this week and I told them to call me when they knew.The next day I went down to my local NRCS office and got some info including a contractor list.I'm giving them to Wednesday and I will start calling others.The soil scientist was not in last week when I was there but I got to talk to him today on the phone.He said he knows my soil types well and that they should work good,even the rockier stuff that I was worried about.So that sounds great.But he also told me he would only build a pond in January-March so it fills up before the dirt can crack.I've had others tell me they like it to take longer to fill so you can get grass to grow first.Has anyone had trouble with building a pond because the didn't do it January-March?I really don't want to wait almost a year to build it!lol!

Last edited by Bobbss; 04/24/17 12:43 PM.

Bob