Quick update,

I have rented a skid loader for next week to finish the last remaining work before winter. Much of the work is left over from the excavator not finishing.

We need to finishing laying rock in several areas to complete the walking path around the land.

Build a 15 by 15 pad for the main shed.

Move the boulders found when digging. I want to sit around the beach area.

Fill in the 300 ft trench.

Scrap out the upper section of the silt pond, re-line with clay, expand the lower section of the silt pond.

Fill in a few gulleys in the the main pond caused by spring rains.

haul out some of the fallen trees laid by the farmer several years ago.

build the rock pier.

I have 86 machine hours Monday to Sunday, we are driving with flashlights if we have to.

Should be fun!!!

The catfish pond is about 1/3 full, hoping for a localized 100 feet of snow in the Judah Wisconsin area this winter


13 acres,
5 ponds 1 still working
FHM, Shiners, CC, SMB, WE, Yellow Perch
living the dream




Can't have everything...where would you put it?