Finally, a break in the weather! We have lowered the lake four feet and now only 50% of the surface area remains. This was very frustrating as we would lower it and then get rain and it would fill right back up. It took almost a month to get a break in the weather.
Jerry Donner came in and had his team push dirt out even further by creating a mini dam. We want to get the cabin surrounded by as much water as possible (shooting for 90%).
Once that was done, we spent the weekend pumping out the area as there was a small leak in the mini-dam.
Monday, the work started.
The site was then measured, trenches dug, and the foundation poured.
Here is the current status. Scott