The dam is estimated to be 1/2 complete. The backside is mostly done, and about 1/3 of the front.

We piped the spring into a spring box, made of a 55 gallon drum. The pipe will go straight to the top of the dam. Another will go along the bottom and through the dam. This will take pressure off the keyway.

We poured 4 yards of concrete over most of the spring box, and formed a blob. This will protect it, over the years, and from the equipment.