Just a quick update on the project and photo. We went out last Monday to shot some elevations and dig some test holes. The digging proved to be more disappointing than expected. We knew there was limestone from the survey and well info but the extent of the rock was far more than expected or desired. The plot is only 13 acres so there is not alot of room. The rock can be used to build an extension to the road and for the driveway and to rip rap but with so much rock there may be very little clay.

As the saying 'you can build a pond just about anywhere as long as you have enough m money". I know there are options but they start to move the cost arrow upwards.
Excavator is working up a design and cut and fill print out.