Well as I stated in prior updates. This is going to be a tough decision on which contractor to use. I have 2 bids in so far and there is only 441.00 difference in the bids! I would never have thought it would be that close but it just proves if you do as much up front planning as possible it can help tremendously. I think having the NCRS come out and shoot the property and write up a plan that calculates pipe size, dam length and yards of dirt needing moved etc. helped a lot. It will be curious to see what the 3rd bid comes in at.

Last edited by MWB; 05/03/19 05:47 PM.