Pictures of installing the overflow pipe. I used rubber anti-seep collars in the big pond, but the 3pt tractor mounted cement mixer was going to be used to make concrete ends for the overflow pipe, so I just used cement anti-seep collars. Backhoe dug trench for pipe, then we hand dug slot on sides and bottom of trench for anti-seep, then poured concrete.

Definitely a farmer done job. Not professional at all but functional.

Notice new dam portion to the left in the first picture. That is where the rocked overflow used to be.

The main pond is about 2' low at this point which is mid August. The flat concrete for the water to hit when it exits will be a few inches under water when the main pond is at full pool. The outlet pipe will be about 8" above the main pond full pool level so fish can not swim up the pipe to the forage pond. Good time to work on ponds when they are low. Hard on water quality and fish.

Attached Images
007.JPG 008.JPG 009.JPG 010.JPG
Last edited by snrub; 10/13/14 12:00 AM.

John

I subscribe to Pond Boss Magazine