The 1st pond attempt is a big sandy leaker, though we didn't believe it'd hold water without some real follow up effort when dug. In planning the 0.1 acre, 4400sq.ft., do over pond, I'll need to either EPDM line it, total pond cost $6900 or have lots of clay hauled in $7000.
My question: Roughly, how much does hauled in clay pack down? I'm using 2 units clay nets 1 unit after packing, need 18 loads. I know the packing can vary, but can I reasonably adjust my clay cost up or down? Assume a moderate moisture level. Also guestimating that a 10 wheel dump truckload carries about 400+ cu.ft. Hope I'm not off on that number.
Last edited by SoSauty; 08/20/14 10:33 PM. Reason: adjust calculations