Well, it has been a few months but they are going to start excavating this week. They are going to be taking out about 40,000 cubic yards of clay, and then putting the top soil back on top. should be between 12-14 feet for 50% of the pond. Maybe even 75%.

I am working on an outline of the new pond and putting together a list of questions for y'all before they drain the pond on Friday.

What I need to confirm ASAP is the slope. Would a 3:1 slope to a depth of atleast 10ft all the way around the pond be ideal?

Or should change the slope to be more steep after 6ft of depth?

They are going to be putting the plans in CAD and sending me a PDF tomorrow. I've told them 3:1 slope for now. Hopefully I was correct.

Thanks